Project Progress (Jan 2026 – Present)

Work Completed to Date

After entering Japan on January 7, 2026, Yorisou began preparing a community-based mobility pilot in Fukuoka.

Key progress to date includes:

  • Initiated company setup as a GK (Godo Kaisha)
  • Secured a shared office base in Imajuku, Nishi Ward, Fukuoka
  • Launched the official website
  • Organized the pilot’s basic design and operational structure
  • Conducted initial research on mobility challenges in an aging society

Key Plan Through July 2026

Yorisou will proceed with phased preparation through July 2026.

Phase 1 (March)

  • Complete company establishment
  • Set up the operating foundation (bank account, contracts)

Phase 2 (April–May)

  • Conduct local interviews and select candidate pilot fields
  • Design a small-scale pilot model (3–5 vehicles)
  • Establish safety management and insurance policy

Phase 3 (June)

  • Finalize the pilot execution plan
  • Finalize the business plan package
  • Coordinate with local government and community stakeholders

Principles

Yorisou aims to build a sustainable community mobility model through small-scale pilots without relying on government budgets. We will validate practical operations aligned with local daily routes, emphasizing safety and continuity.